(function(i,s,o,g,r,a,m){i['GoogleAnalyticsObject']=r;i[r]=i[r]||function(){ (i[r].q=i[r].q||[]).push(arguments)},i[r].l=1*new Date();a=s.createElement(o), m=s.getElementsByTagName(o)[0];a.async=1;a.src=g;m.parentNode.insertBefore(a,m) })(window,document,'script','//www.google-analytics.com/analytics.js','ga'); ga('create', 'UA-57279409-2', 'auto'); ga('send', 'pageview');
 

(EW) Campus Loop Road for North DeSoto Schools

Project Location:  Stonewall, LA
Project Features:  22,500 Cubic Yard Earthwork Site Balance
9,500 Ton of Aggregate Sub Base
2,000 Lineal Feet Reinforced Concrete Pipe
28,000 Square Yards of Concrete Road Pavement
Completion Date:  September, 2013

Fessler & Bowman, Inc. was the Prime Contractor for this project and self performed the complete Earthwork and Concrete scope. As the name of the project indicates this was a newly constructed loop road around the existing K-12 North DeSoto Schools. Logistics were a challenge as a substantial amount of the work was perfromed while school was in session.