(function(i,s,o,g,r,a,m){i['GoogleAnalyticsObject']=r;i[r]=i[r]||function(){ (i[r].q=i[r].q||[]).push(arguments)},i[r].l=1*new Date();a=s.createElement(o), m=s.getElementsByTagName(o)[0];a.async=1;a.src=g;m.parentNode.insertBefore(a,m) })(window,document,'script','//www.google-analytics.com/analytics.js','ga'); ga('create', 'UA-57279409-2', 'auto'); ga('send', 'pageview');
 

JP Morgan Chase Data Center Addition

Project Location:  Belleville, MI
Project Features:  6,200 Cubic Yards of Concrete
100,000 Square Feet of Concrete Slab on Grade
50,000 Square Feet of Elevated Slab on Deck
Complete Building Foundations & Site Concrete
Completion Date:  August, 2007

This project was a 38,000 square foot addition and 60,000 square foot renovation of the existing data center which remained in full operation during the entire construction process. The project required 3,000+ lineal feet of utility trenches throughout the footprint of the renovated building area posing a unique challenge to the placement of the slab on grade concrete.