Android Industries

Android Industries

Project Location:  Flint, MI
Project Features:  19,000 Cubic Yards of Concrete
460,000 Square Feet of 8? Slab on Grade
170,000 Square Feet of 8? Concrete Pavement
Complete Concrete Building Foundations & Site Concrete
Completion Date:  June, 2006

Being able to complete this project in a four month time frame was a deciding factor on Fessler & Bowman being awarded this project. F&B started the building foundations in mid February and placed the last yard of site concrete in mid June while fighting through some very difficult winter and site conditions. Large slab placements were used to complete the 460,000 square feet of interior slab on grade and we were able to accomplish this by using our Somero Laser Screed.